Billed to date vs the $604,213 contract sum.
Amount billed each month (bars) and the running cumulative total (gold line).
Application #001's month is inferred from numbering; its file was not in the set provided.
Each application is the amount billed that month; cumulative is the running total completed to date.
| App | Month | Invoice date | Payment due | This invoice | Cumulative | Complete | Status |
|---|---|---|---|---|---|---|---|
| #001 | Jul 2026 | — | — | $19,034.28 | $19,034.28 | 3.15% | Prior |
| #002 | Aug 2026 | 2026-08-31 | 2026-09-28 | $57,749.80 | $76,784.08 | 12.71% | Due |
| #003 | Sep 2026 | 2026-09-30 | 2026-10-12 | $49,376.38 | $133,886.06 | 22.16% | Due |
From Application #003 (Sep 30, 2026). Billed to date and balance to finish per cost code.
| Code | Description | Scheduled | Billed | Progress | Balance |
|---|---|---|---|---|---|
| 01-010 | Project Manager | $22,500.00 | $2,750.00 | 12% | $19,750.00 |
| 01-012 | Superintendent | $10,000.00 | $4,500.00 | 45% | $5,500.00 |
| 01-500 | Temporary Facilities not started | $600.00 | $0.00 | 0% | $600.00 |
| 01-542 | Scaffolding & Platforms over budget | $6,000.00 | $7,400.00 | 123% | $-1,400.00 |
| 01-580 | Debris Removal | $6,000.00 | $2,650.00 | 44% | $3,350.00 |
| 01-740 | Cleaning | $3,400.00 | $1,487.50 | 44% | $1,912.50 |
| 02-000 | Demolition | $17,000.00 | $9,516.00 | 56% | $7,484.00 |
| 03-050 | Concrete | $30,000.00 | $20,475.20 | 68% | $9,524.80 |
| 05-500 | Metal Fabrications not started | $2,400.00 | $0.00 | 0% | $2,400.00 |
| 06-100 | Rough Carpentry | $13,500.00 | $7,531.00 | 56% | $5,969.00 |
| 06-200 | Ext. Finish Carpentry | $162,500.00 | $9,632.87 | 6% | $152,867.13 |
| 06-300 | Int. Finish Carpentry | $14,500.00 | $6,587.50 | 45% | $7,912.50 |
| 06-400 | Cabinet grade Wdwk. | $5,000.00 | $1,788.41 | 36% | $3,211.59 |
| 07-100 | Damp / Waterproofing | $3,130.00 | $2,538.89 | 81% | $591.11 |
| 07-200 | Insulation not started | $500.00 | $0.00 | 0% | $500.00 |
| 07-300 | Shingles, Roof Tiles, etc. not started | $32,000.00 | $0.00 | 0% | $32,000.00 |
| 07-600 | Flashing & Sheet Metal not started | $600.00 | $0.00 | 0% | $600.00 |
| 08-500 | Windows | $71,000.00 | $19,218.86 | 27% | $51,781.14 |
| 09-250 | Gypsum Wallboard not started | $20,000.00 | $0.00 | 0% | $20,000.00 |
| 09-300 | Tile | $8,100.00 | $2,087.00 | 26% | $6,013.00 |
| 09-600 | Flooring not started | $3,500.00 | $0.00 | 0% | $3,500.00 |
| 09-900 | Paints & Coatings not started | $32,000.00 | $84.78 | 0% | $31,915.22 |
| 10-800 | Bath, Laundry Access. not started | $2,000.00 | $0.00 | 0% | $2,000.00 |
| 15-100 | Plumbing | $20,400.00 | $17,064.33 | 84% | $3,335.67 |
| 15-400 | Plumbing Fixtures not started | $3,743.00 | $0.00 | 0% | $3,743.00 |
| 15-700 | HVAC not started | $8,000.00 | $0.00 | 0% | $8,000.00 |
| 16-100 | Electrical not started | $20,000.00 | $0.00 | 0% | $20,000.00 |
| 16-500 | Lighting | $2,500.00 | $106.67 | 4% | $2,393.33 |
| 17-020 | Insurance | $5,209.00 | $1,154.19 | 22% | $4,054.81 |
| 17-040 | Overhead | $78,131.00 | $17,312.86 | 22% | $60,818.14 |
| Total | $604,213.00 | $133,886.06 | 22.16% | $470,326.94 |
Largest remaining: Ext. Finish Carpentry — $152,867.13 left of $162,500.00 (6% complete). Most complete: Plumbing 84%, Damp / Waterproofing 81%, Concrete 68%. Eleven lines have not started yet.
Labor timecards, material bills, and sub invoices behind each month's amount, from the GC Detail sheets.
September restated August. September's previous-certificates figure ($84,509.68) is $7,725.60 higher than August's total completed ($76,784.08). Three lines were restated between the applications, which reduced September's current amount due by the same $7,725.60.
| Code | Description | Aug total | Sep “previous” | Change |
|---|---|---|---|---|
| 01-542 | Scaffolding & Platforms | $740.00 | $7,400.00 | +$6,660.00 |
| 17-020 | Insurance | $661.93 | $728.53 | +$66.60 |
| 17-040 | Overhead | $9,928.98 | $10,927.98 | +$999.00 |
| Total restatement | $76,784.08 | $84,509.68 | +$7,725.60 |