Grand View Terrace Construction

170 Grand View · Project UB2212 · Contract 001 · Contractor UrbnBuild (Olivia Lopez, 1311 Church St, San Francisco, CA 94114-3911) · Owner Grand View Res
Contract sum (budget)
$604,213.00
Change orders: $0.00 · Retainage: $0.00
Billed to date
$133,886.06
22.16% of budget · through Sep 30, 2026
Balance to finish
$470,326.94
77.84% of budget remaining
Current payment due (Sep)
$49,376.38
Application #003 · due Oct 12, 2026
Billed if nothing paid yet
$133,886.06
Total completed to date; payment status unconfirmed
Applications received
3
#001, #002 (Aug), #003 (Sep)

Amount due now

$49,376.38 — Application #003, September, due Oct 12, 2026

Progress toward the budget

Billed to date vs the $604,213 contract sum.

22.16% billed — $133,886.06$470,326.94 to finish

Month by month

Amount billed each month (bars) and the running cumulative total (gold line).

$0k$50k$100k$150k$19,034Jul 2026App #001$57,750Aug 2026App #002$49,376Sep 2026App #003cum $19,034cum $76,784cum $133,886
billed that month cumulative billed to date

Application #001's month is inferred from numbering; its file was not in the set provided.

Pay applications

Each application is the amount billed that month; cumulative is the running total completed to date.

AppMonthInvoice datePayment dueThis invoiceCumulativeCompleteStatus
#001Jul 2026——$19,034.28$19,034.283.15%Prior
#002Aug 20262026-08-312026-09-28$57,749.80$76,784.0812.71%Due
#003Sep 20262026-09-302026-10-12$49,376.38$133,886.0622.16%Due

Cost breakdown — schedule of values

From Application #003 (Sep 30, 2026). Billed to date and balance to finish per cost code.

CodeDescriptionScheduledBilledProgressBalance
01-010Project Manager$22,500.00$2,750.00
12%
$19,750.00
01-012Superintendent$10,000.00$4,500.00
45%
$5,500.00
01-500Temporary Facilities not started$600.00$0.00
0%
$600.00
01-542Scaffolding & Platforms over budget$6,000.00$7,400.00
123%
$-1,400.00
01-580Debris Removal$6,000.00$2,650.00
44%
$3,350.00
01-740Cleaning$3,400.00$1,487.50
44%
$1,912.50
02-000Demolition$17,000.00$9,516.00
56%
$7,484.00
03-050Concrete$30,000.00$20,475.20
68%
$9,524.80
05-500Metal Fabrications not started$2,400.00$0.00
0%
$2,400.00
06-100Rough Carpentry$13,500.00$7,531.00
56%
$5,969.00
06-200Ext. Finish Carpentry$162,500.00$9,632.87
6%
$152,867.13
06-300Int. Finish Carpentry$14,500.00$6,587.50
45%
$7,912.50
06-400Cabinet grade Wdwk.$5,000.00$1,788.41
36%
$3,211.59
07-100Damp / Waterproofing$3,130.00$2,538.89
81%
$591.11
07-200Insulation not started$500.00$0.00
0%
$500.00
07-300Shingles, Roof Tiles, etc. not started$32,000.00$0.00
0%
$32,000.00
07-600Flashing & Sheet Metal not started$600.00$0.00
0%
$600.00
08-500Windows$71,000.00$19,218.86
27%
$51,781.14
09-250Gypsum Wallboard not started$20,000.00$0.00
0%
$20,000.00
09-300Tile$8,100.00$2,087.00
26%
$6,013.00
09-600Flooring not started$3,500.00$0.00
0%
$3,500.00
09-900Paints & Coatings not started$32,000.00$84.78
0%
$31,915.22
10-800Bath, Laundry Access. not started$2,000.00$0.00
0%
$2,000.00
15-100Plumbing$20,400.00$17,064.33
84%
$3,335.67
15-400Plumbing Fixtures not started$3,743.00$0.00
0%
$3,743.00
15-700HVAC not started$8,000.00$0.00
0%
$8,000.00
16-100Electrical not started$20,000.00$0.00
0%
$20,000.00
16-500Lighting$2,500.00$106.67
4%
$2,393.33
17-020Insurance$5,209.00$1,154.19
22%
$4,054.81
17-040Overhead$78,131.00$17,312.86
22%
$60,818.14
Total$604,213.00$133,886.0622.16%$470,326.94

Largest remaining: Ext. Finish Carpentry — $152,867.13 left of $162,500.00 (6% complete). Most complete: Plumbing 84%, Damp / Waterproofing 81%, Concrete 68%. Eleven lines have not started yet.

What was billed — item detail

Labor timecards, material bills, and sub invoices behind each month's amount, from the GC Detail sheets.

Application #002 — Aug 2026 — $57,749.80
01-010 — Project Manager$1,375.00
  • Michael Donohue — 11 hrs × $125.00
01-012 — Superintendent$4,250.00
  • Bruce Wickstrom — 34 hrs × $125.00
01-542 — Scaffolding & Platforms$740.00
  • Banton Scaffold, Inc. — $740.00
01-580 — Debris Removal$700.00
  • Carlos Castellanos — debris hauling + dumping — $700.00
01-740 — Cleaning$1,487.50
  • Carlos Castellanos — 4 hrs × $85.00 = $340.00
  • Ernesto Gutierrez — 13.5 hrs × $85.00 = $1,147.50
02-000 — Demolition$7,476.00
  • EG Construction — demo — $4,416.00
  • Ernesto Gutierrez — 36 hrs × $85.00 = $3,060.00
03-050 — Concrete$18,473.20
  • EG Construction — $7,390.00
  • Carlos Castellanos — 69.5 hrs × $85.00 = $5,907.50
  • Excel Site Service — debris load — $1,250.00
  • Ernesto Gutierrez — 10.5 hrs × $85.00 = $892.50
  • Bauman Redi-Mix — volumetric concrete — $835.40
  • Bauman Redi-Mix — line pumps — $686.72
  • CA Waterproofing — bonding agent — $510.20
  • Broadmoor Landscape — drain rock — $302.86
  • Broadmoor Landscape — drain sleeve — $216.82
  • Metal Man — supplies — $200.96
  • Discount Builders — supplies — $125.44
  • Home Depot — $49.59
  • Lowe's — $46.59
  • Discount Builders — supplies — $28.22
  • Lowe's — $18.46
  • Discount Builders — supplies — $11.94
06-100 — Rough Carpentry$1,183.20
  • Carlos Castellanos — 8 hrs × $85.00 = $680.00
  • Gustavo Brandan — 5.92 hrs × $85.00 = $503.20
06-400 — Cabinet grade Wdwk.$1,788.41
  • West Elm — hardware — $1,788.41
08-500 — Windows$340.00
  • Carlos Castellanos — 4 hrs × $85.00 = $340.00
15-100 — Plumbing$11,864.33
  • Hollon Plumbing — sub invoice — $11,864.33
16-500 — Lighting$106.67
  • Supply House — supplies — $106.67
17-020 — Insurance$497.84
  • Insurance markup — $497.84
17-040 — Overhead$7,467.65
  • Overhead markup — $7,467.65
Application #003 — Sep 2026 — $49,376.38
01-010 — Project Manager$1,375.00
  • Bruce Wickstrom — 11 hrs × $125.00
01-580 — Debris Removal$1,950.00
  • Excel Site Service — debris hauling + dumping — $1,200.00
  • Carlos Castellanos — debris hauling + dumping — $750.00
02-000 — Demolition$2,040.00
  • Carlos Castellanos — 24 hrs × $85.00 = $2,040.00
03-050 — Concrete$2,002.00
  • Beronio Lumber — September statement — $1,969.05
  • Beronio Lumber — September statement — $32.95
06-100 — Rough Carpentry$6,347.80
  • Matt Silva — 40 hrs × $85.00 = $3,400.00
  • Carlos Castellanos — 24 hrs × $85.00 = $2,040.00
  • Gustavo Brandan — 10.68 hrs × $85.00 = $907.80
06-200 — Ext. Finish Carpentry$9,632.87
  • Beronio Lumber — September statement — $5,232.21
  • Carlos Castellanos — 40 hrs × $85.00 = $3,400.00
  • Beronio Lumber — September statement — $880.11
  • Center Hardware — $120.55
06-300 — Int. Finish Carpentry$6,587.50
  • Gustavo Brandan — 77.5 hrs × $85.00 = $6,587.50
07-100 — Damp / Waterproofing$2,538.89
  • Beronio Lumber — September statement — $2,538.89
08-500 — Windows$2,720.00
  • Carlos Castellanos — 32 hrs × $85.00 = $2,720.00
09-300 — Tile$2,087.00
  • Creative Tile & Marble Inc. — tiles — $2,087.00
09-900 — Paints & Coatings$84.78
  • Tamalpais Paint & Color — hardware — $84.78
15-100 — Plumbing$5,200.00
  • Hollon Plumbing — sub invoice — $5,200.00
17-020 — Insurance$425.66
  • Insurance markup — $425.66
17-040 — Overhead$6,384.88
  • Overhead markup — $6,384.88

Flags and notes

September restated August. September's previous-certificates figure ($84,509.68) is $7,725.60 higher than August's total completed ($76,784.08). Three lines were restated between the applications, which reduced September's current amount due by the same $7,725.60.

CodeDescriptionAug totalSep “previous”Change
01-542Scaffolding & Platforms$740.00$7,400.00+$6,660.00
17-020Insurance$661.93$728.53+$66.60
17-040Overhead$9,928.98$10,927.98+$999.00
Total restatement$76,784.08$84,509.68+$7,725.60